The detour route for phase 3 of the Picton Main Street reconstruction will be in place until Friday, September 2.
The detour route was originally scheduled to end as of August 26; however, due to complications resulting from unexpected underground utility encounters, it will be necessary to extend the date of the phase 3 completion until September 2.
Northbound and southbound traffic will continue to be detoured via Picton Main Street, Walton Street, King Street, Paul Street, Jane Street, Queen Street, Johnson Street to Picton Main Street. View the detour map.
Local property access will be maintained during the detour.
More information about the reconstruction project is available on the County website. For more information, contact the County of Prince Edward at 613.476.2148 ext. 1023, 613.962.9108 ext. 1023, or info@pecounty.on.ca.