The reconstruction of Picton Main Street between Bridge Street and Johnson Street will begin on Monday, July 4.
The scope of the project includes the following work:
- Replacement of the existing sanitary sewer and services
- Replacement of the existing watermain and services
- Storm sewer replacement
- Complete road reconstruction with new curb and gutters, sidewalks, asphalt pavement, and decorative street lighting
RW Tomlinson Limited, the contractor for this project, will complete the work in phases to minimize the impact to pedestrian and vehicular traffic.
Phase 1: July 4 until July 25
Initial construction will begin at the Bridge Street intersection with sewer installation on Bridge Street.
Traffic impact: The section of Picton Main Street between Bridge Street and the south side of Paul Street will be closed to traffic with detour routes in place. Traffic will be detoured via Picton Main Street, Walton Street, King Street, Paul Street to Picton Main Street. View the detour map
Phase 2: July 25 until August 15
Picton Main Street between Bridge Street and the south side of Paul Street will be closed to traffic and the intersection of Paul Street and Picton Main Street will be open to northbound and southbound traffic.
Traffic impact: Traffic will be detoured via Picton Main Street, Walton Street, King Street, Paul Street to Picton Main Street. View the detour map
Phase 3: August 15 until September 1
Picton Main Street between Bridge Street and Paul Street will be closed to traffic including the intersection of Picton Main Street and Paul Street.
Traffic impact: Northbound and southbound traffic will be detoured via Picton Main Street, Walton Street, King Street, Paul Street, Jane Street, Queen Street, Johnson Street to Picton Main Street. View the detour map
Phase 4: September 1 until September 12
Picton Main Street between Bridge Street and the south side of Paul Street will be closed to traffic. Construction begins on Picton Main Street north of Paul Street.
Traffic impact: Northbound traffic permitted on Picton Main Street from Paul Street to Johnson Street. Traffic will be detoured via Picton Main Street, Walton Street, King Street, Paul Street, Jane Street, Johnson Street. View the detour map
Phase 5: September 12 until October 21
Picton Main Street between Bridge Street and Paul Street will be open to northbound and southbound traffic.
Traffic impact: Northbound traffic between Paul Street and Johnson Street permitted and southbound traffic will be detoured via Picton Main Street, Johnson Street, Jane Street, Paul Street to Picton Main Street. View the detour map
Phase 6: October 21 until November 14
Picton Main Street will be closed to through traffic between the north side of Paul Street through the intersection of Johnson Street.
Traffic impact: Traffic will be detoured via Picton Main Street, Paul Street, Jane Street, Queen Street, Johnson Street, Gladstone Street, Maple Street, to Picton Main Street. View the detour map
Click here to learn more. For more information, contact the County of Prince Edward at 613.476.2148 ext. 1023, 613.962.9108 ext. 1023, or info@pecounty.on.ca.