RW Tomlinson Limited is concluding work on Phase 3 of the Picton Main Street reconstruction project for 2025.
The road will return to two-lane traffic with no signals as of Friday, December 12.
This past fall, work crews completed the sanitary and storm sewer work on the west side of the road from #454 County Road 49 to Fawcett Avenue. A single layer of temporary asphalt was placed to allow the municipality to reopen the road during the winter months. The surface will be maintained throughout the winter. A new roadway will be installed when the entire project is completed.
RW Tomlinson Limited will resume construction in the spring 2026 and continue work until December 2026. One lane of traffic will be maintained at all times and alternate routes will be identified.
Work will include:
- Sanitary and storm sewer replacement and extension from Fawcett Avenue to Folkard Lane.
- Watermain replacement from #454 County Road 49 to Folkard Lane
- Installation of new roadway, curbs, sidewalk and street lighting from #454 County Road 49 to Folkard Lane
The municipality will provide an update prior to construction resuming in the spring. To sign up for notices, click here. Notices will also appear in the local newspapers and on the municipality’s Facebook, Twitter, and Instagram accounts.
Visit the project page on the municipal website for more information. If you have an issue during construction, please contact Jeff Shortt, Project Manager, at 613.476.2148 extension 1007 or email jshortt@pecounty.on.ca.
Please note: The County of Prince Edward provides this information as a service to the general public. While we do our best to provide accurate information, construction projects and associated service disruptions are subject to change based on weather, road, traffic, and other uncontrollable conditions.