The County of Prince Edward is updating the community on the Wellington trunk watermain and sanitary sewer project.
Recently completed works:
- The contractor has made the final watermain connection and Consecon Street has now reopened to traffic.
- The contractor has installed the final section of sewer forcemain across Consecon Street.
- Testing has confirmed that there are no issues with the installation of the new sanitary sewer
- The contractor has installed a yard hydrant at the end of West Street.
- The electrical contractor continues to make progress on installing new wiring for the new sewage pumping station.
Current works:
- Site grading and installation of fencing and bollards is now taking place at the sewage pumping station.
- The electrical subcontractor is continuing to install electrical duct banks to facilitate Hydro One’s hydro connection to power the new sewage pumping station.
- Final testing and commissioning of the new sewage pumping station.
Reminder:
- The Millennium Trail remains closed between Consecon Street and Wharf Street while the sewage pumping station is commissioned.
If you have an issue or concern, please contact Chris Timpson, Project Manager, County of Prince Edward, at 613.476.2148 extension 2035 or email ctimpson@pecounty.on.ca.
Please note: The County of Prince Edward provides this information as a service to the general public. While we do our best to provide accurate information, construction projects and associated service disruptions are subject to change based on weather, road, traffic, and other uncontrollable conditions.