The installation of a water trunk main connection in Wellington will impact traffic on Belleville Street on Friday, September 26, 2025. In addition, the bulk water filling stations at the Wellington and District Community Centre and the 3″ bulk station at the Wellington water tower will be temporarily out of service that day.
Please note: this work was previously scheduled to take place on Thursday, September 25, 2025. The date has changed due to the high probability of rain on that day.
- Belleville Street across from the water tower will be reduced to one lane. Flaggers will control the flow of traffic through the construction area. Motorists and pedestrians are asked to avoid the construction area and travel alternate routes, if possible.
- Work will take place from 7 am to 7 pm and is expected to be completed the same day.
- Heavy equipment may limit visibility in the area and noise levels will be elevated for the duration of the work.
- Customers requiring bulk water filling service during this time are asked to use the Picton (15 MacSteven Drive) or Carrying Place (21651 Loyalist Parkway) bulk loading stations.
- This work is required as part of the Wellington trunk watermain and sanitary sewer construction project. The municipality expects the majority of the project to be completed by the end of 2025 with some trail restoration happening in the spring of 2026.
- For more information, contact the County of Prince Edward at 613.476.2148 extension 1023, 613.962.9108 extension 1023, or info@pecounty.on.ca.
Please note: The County of Prince Edward provides this information as a service to the general public. While we do our best to provide accurate information, construction projects and associated service disruptions are subject to change based on weather, road, traffic, and other uncontrollable conditions.