Prince Edward County Municipal Services

Business

Find the info you need on relocating, starting or expanding your business in Prince Edward County.

Visit

Explore what Prince Edward County has to offer for residents and visitors alike.

 

 

County provides update on Bloomfield Main Street rehabilitation project

March 25, 2026

The County of Prince Edward shared more information about the construction schedule and logistics for the Bloomfield Main Street rehabilitation project at a public information centre (PIC) on Monday, March 24. Construction is scheduled to begin on Monday, March 30.

Click here to view the information boards displayed at the PIC

If you were unable to attend the in-person PIC on Monday, a virtual event will occur on Thursday, March 26 beginning at 6 pm. Click here to access the session.

The construction schedule, which is subject to change based on weather and other conditions, is as follows:

Week 1 (March 30 – April 3)

  • Equipment mobilization
  • Signage, traffic control, locates and pre-construction building surveys
  • Mark curb and sidewalk for removal
  • Storm sewer replacement beginning at Corey Street

Week 2 – 5 (April 6 – May 1)

  • Storm sewer replacement and curb/sidewalk/boulevard removal continues west
  • New curb/sidewalk/boulevard starts at Corey Street and continues west

Week 6 (May 4 – 8)

  • Full depth asphalt milling begins at Corey Street and continues west
  • Fine grade road
  • New curb/sidewalk/boulevard continues west

Week 7 (May 11 – 15)

  • New decorative concrete boulevard
  • Pave base course asphalt
  • Temporary line painting
  • Adjust manhole lids

Week 8 – 9 (May 18 – 29)

  • Adjust manhole lids
  • Pave top course asphalt
  • Permanent line painting

Week 10 (June 1 – 5)

  • Miscellaneous asphalt repairs (driveways and boulevards)
  • Miscellaneous line painting

Week 11 (June 8 – 12)

  • Post-construction building surveys
  • Remove signage, traffic control and equipment (demobilization)

Weeks 12 – 13 (June 15 – 26)

  • No planned work

Lane closures and parking

Lane closures:

  • Daily single lane closures will occur only in the active work area. Traffic will be controlled by using portable lights or flaggers
  • Two-way traffic will resume at the end of each working day

Parking:

  • Public parking remains available at the public parking lot at 289 Bloomfield Main Street (Town Hall) and the public lot adjacent to the Corey Street intersection.
  • Public parking will also be available at the Emmanuel Baptist Church (240 Bloomfield Main St, Bloomfield)

Scope of the Work

  • Removal of existing asphalt surface
  • Placement of 100mm of new hot mix asphalt
  • Replacement of approximately 10 storm sewer sections
  • Replacement of deteriorated curb sections
  • Minor sidewalk panel replacements
  • Replacement of west boulevard with new asphalt
  • Replacement of east boulevard with stamped concrete (provisional)
  • Line painting

Additional information

The 1.0 km stretch of Bloomfield Main Street between Corey Street and Wellington Street is considered a “connecting link” between two provincial highways. The Province of Ontario is covering 90 per cent of the cost to resurface this section of road under the Connecting Links program.

Bloomfield Main Street is beginning to deteriorate with significant cracking, especially down the centre line of the road. Resurfacing will extend the life of the road, providing a smooth, safe surface for all traffic.

If you have questions or concerns about the project, please contact Garrett Osborne, Project Manager, at 613.476.2148 extension 2002 or email gosborne@pecounty.on.ca.

Sign up to receive news and notices from the municipality.

Please note: The County of Prince Edward provides this information as a service to the general public. While we do our best to provide accurate information, construction projects and associated service disruptions are subject to change based on weather, road, traffic, and other uncontrollable conditions.

 

Share This:
Share
Tweet
Save

Related News & Notices

Roadside brushing operations throughout the County April 7 – May 29

Street sweeping gets underway April 7

Outbreak over at H.J. McFarland Memorial Home

Register now to renew or replace your PEC Summer Pass

April is Dig Safe Month: Click Before You Dig

Macaulay Heritage Park museum closure extended into April