Paving on Bloomfield Main Street to begin May 21

May 20, 2026

Base coarse asphalt paving on Bloomfield Main Street from Corey Street to Wellington Street will begin on Thursday, May 21.

The contractor will attempt to complete this paving in one day. However, paving may continue during the morning on Friday, May 22.

During the paving operation, motorists should plan for significant delays, including extended wait times and intermittent stoppages similar to those experienced during recent milling operations. Allow extra travel time or consider alternate routes where feasible. Substantial traffic delays are anticipated. All businesses remain open during the paving with pedestrian access maintained.

Top coarse asphalt paving is expected to occur late next week or the first week of June. Once the exact schedule for top coarse asphalt paving is confirmed, a public service announcement (PSA) will be issued. Click here to receive updates on this project.

Parking during construction

Throughout construction, free parking is available at the following locations:

  • Emmanual Baptist Church (240 Bloomfield Main St, Bloomfield)
  • 257 Bloomfield Main Street (beside Bloomfield Public House)
  • Bloomfield Town Hall (289 Bloomfield Main Street)

Additional information

The municipality is providing weekly updates every Friday throughout the project as well as other updates as required. Visit the County website and sign up to receive these updates in your inbox.

The municipality is resurfacing Bloomfield Main Street from Corey Street to Wellington Street in 2026. The project will also include line painting, storm sewer repairs, concrete curb and sidewalk repairs. Learn more about the project.

If you have any questions or concerns, contact Garrett Osborne at gosborne@pecounty.on.ca or call 613.476.2148 extension 2002.

Share This:
Share
Tweet
Save

Related News & Notices

Temporary changes to garbage and recycling collection June 29 – July 1 for Canada Day holiday

Traffic disruptions in Picton for Pride Parade June 20

Agenda now available for June 17 Planning and Development Committee

PECelebrates returns June 14 – July 1

Traffic disruptions on section of County Road 10 (Cherry Valley) June 15

Watermain flushing and hydrant maintenance (Rossmore/Fenwood Gardens) begins June 15