Prince Edward County Municipal Services

Business

Find the info you need on relocating, starting or expanding your business in Prince Edward County.

Visit

Explore what Prince Edward County has to offer for residents and visitors alike.

 

 

Bloomfield Main Street Rehabilitation

The County of Prince Edward is resurfacing Bloomfield Main Street from Corey Street to Wellington Street in 2026. The project will also include line painting, storm sewer repairs, and concrete curb and sidewalk repairs.

kilometre
0
Total project cost
$ 0 M
Provincial funding
0 M
Target completion
0

Project Overview

The project involves removing the existing asphalt roadway and repaving with new hot mix asphalt. Following paving, the contractor will repaint the lines to match exactly the line markings that existed before construction.

The only underground work associated with this project are minor storm sewer repairs. Sections of storm sewers will be replaced to protect the investment of new asphalt. This work will require an excavator to dig a trench at each location. No watermain work is needed, and there are no sanitary sewers in Bloomfield.

Damaged sections of concrete curb and sidewalk will be removed and replaced where needed. The majority of required curb replacement is between Stanley Street and Wellington Street.

Project Impacts

Pedestrians:

  • Pedestrian access to businesses and homes will be maintained at all times.
  • Pedestrians will not be allowed to cross within the work zone. In the event that a sidewalk closure is required, signs will be installed directing pedestrians where to cross.
  • During sidewalk repairs, signs will be installed directing pedestrians where to walk.

Traffic:

  • Traffic may be reduced to one lane along Bloomfield Main Street at times to accommodate construction. During this time, traffic in each direction will proceed alternately as directed by flagging personnel.
  • Portable variable messaging and advisory signs will be installed at numerous locations.

Deliveries:

  • The municipality and the contractor will work with businesses and property managers to accommodate deliveries and loading, as well as passenger drop off/pick up. 

Municipal services:

  • Emergency access for paramedics, police, and fire services will be accommodated at all times.
  • Garbage, green bin, and recycling collection will continue on the regular schedule.
  • Where necessary, the contractor will bring waste bins to a designated location for collection and return the empty bins to the appropriate address each week.
  • Residents are advised to label their bins with their address to ensure proper return.

Project Status

County Council has awarded the tender for this project to Drew Harrison Haulage Ltd. Construction began in April 2026.

Funding Announcement
Geotechnical Investigation
Detailed Design
Procurement
Construction
Demobilization

Timeline

January 2026 – March 2026

Project Design and Tendering

  • Design complete
  • Consultation with public and business community
  • Construction tender issued
  • Tender awarded
January 2026 – March 2026

April 2026

Site Preparation

  • Site preparation
  • Construction begins
April 2026

April 2026

Construction Begins

Week 1 (March 30 – April 3)

  • Equipment mobilization
  • Signage, traffic control, locates and pre-construction building surveys
  • Mark curb and sidewalk for removal
  • Storm sewer replacement beginning at Corey Street

Weeks 2 – 5 (April 6 – May 1)

  • Storm sewer replacement and curb/sidewalk/boulevard removal continues west
  • New curb/sidewalk/boulevard starts at Corey Street and continues west
April 2026

May 2026

Construction Continues

Week 6 (May 4 – 8)

  • Full depth asphalt milling begins at Corey Street and continues west
  • Fine grade road
  • New curb/sidewalk/boulevard continues west

Week 7 (May 11 – 15)

  • New decorative concrete boulevard
  • Pave base course asphalt
  • Temporary line painting
  • Adjust maintenance hole lids

Weeks 8 – 9 (May 18 – 29)

  • Adjust maintenance hole lids
  • Pave top course asphalt
  • Permanent line painting
May 2026

June 2026

Construction Concludes

Week 10 (June 1 – 5)

  • Miscellaneous asphalt repairs (driveways and boulevards)
  • Miscellaneous line painting

Week 11 (June 8 – 12)

  • Post-construction building surveys
  • Remove signage, traffic control and equipment (demobilization)

Weeks 12 – 13 (June 15 – 26)

  • No planned work
June 2026

Budget and Funding

The Province of Ontario is covering 90 per cent of the project costs under the Connecting Links program. The municipality received $2,058,969 through the Connecting Links Program, which provides dedicated provincial funding for road and bridge projects on designated connecting link highways.

The remaining $256,100 for the project will come from the municipality’s Reserve for Roads Construction – Urban.

Resources and Updates

Documents

Council report from March 10, 2026 awarding the construction tender to Drew Harrison Ltd. 

Council report from December 9, 2025 authorizing the execution of the Connecting Links Program Contribution Agreement between the municipality and the Crown (as represented by the Ministry of Transportation. 

Public Information Centre #1 — February 2, 2026

Public Information Centre #2 — March 23, 2026

Recent Updates

  • April 17, 2026: Weekly update #3. >> Read more
  • April 10, 2026: Weekly update #2. >> Read more
  • April 2, 2026: Weekly update #1. >> Read more
  • March 25, 2026: County shares more information about the construction schedule and logistics. >> Read more
  • March 16, 2026: Learn more about the project at a second public information centre. >> Read more
  • March 11, 2026: The municipality awards contract for project to Drew Harrison Haulage Ltd. >> Read more
  • February 20, 2026: The municipality provides a summary of feedback received at the public information centre. >> Read more
  • January 20, 2026: Learn more about Bloomfield Main Street resurfacing project at a public information centre on February 2. >> Read more
  • October 10, 2025: Inspection of storm sewers on Tuesday, October 14 and Wednesday, October 15 could cause minor traffic disruptions. >> Read more
  • September 18, 2025: Traffic disruptions on Bloomfield Main Street September 22 as contractors complete design work for the project. >> Read more
  • May 16, 2025: County receives $2 million from province to resurface portion of Bloomfield Main Street. >> Read more

 

Stay informed as the project advances.

Follow County updates or sign up for notifications.

Want to know more about other Prince Edward County news, projects and initiatives? You may also be interested in the following:
Sign up for monthly municipal newsletter
Sign Up for Municipal Notices, PSAs, News Releases
Sign Up for Flood Updates

Key Contacts

Jeff Shortt

Temporary Project Manager, County of Prince Edward

Phone: 613.476.2148 ext. 1007

Pat Schick

Project Manager, Jewell Engineering

Phone: 613.969.1111                  

Customer Service

County of Prince Edward

Phone: 613.476.2148 ext. 1023