Updated detour route for Picton Main Street reconstruction in effect beginning July 24

July 13, 2023

July 13, 2023

A revised detour route for the Picton Main Street reconstruction project will be in place beginning Monday, July 24.

  • A full closure of Picton Main Street between Johnson Street and Division Street will be in effect. Access to properties will be maintained during the road closure.
  • Picton Main Street between Division Street and McFarland Drive will be local traffic only. This includes the hospital and medical centre. Access to the fairgrounds entrance will be from Bay Street.
  • Through traffic on Picton Main Street will continue to be detoured along Johnson Street, MacSteven Drive, and McFarland Drive.
  • The intersection of Johnson Street and MacSteven Drive has been converted to a three-way stop.
  • View the updated detour map

Project Background

The Picton Main Street reconstruction project began on Monday, June 5. The project, which will span from Johnson Street to 250 metres east of Spencer Street, includes the following work:

  • Installation of new underground infrastructure including watermains, sanitary sewers, and storm sewers.
  • Roadway reconstruction with new concrete curb and gutters, concrete sidewalks, and a new asphalt roadway surface.

RW Tomlinson Limited, the contractor for this project, is completing the work in three phases to minimize the impact to pedestrian and vehicular traffic.

Phase 1 will be conducted between Johnson Street and Bay Street until late August.

Phase 2 work will be conducted between Bay Street and Spencer Street beginning in late August with completion in November 2023. Phase 3 work between Spencer Street and approximately 250 metres east of Spencer Street will take place in 2024.

Quinte Transit’s pick up and drop off locations on Picton Main Street near Life Labs and near Crystal Palace will be temporarily suspended during the construction. Transit riders can get picked up and dropped off at a temporary stop on Johnson Street near the corner of Picton Main Street. Signs are in place at the temporary stop.

More information is available on the County website. For more information, contact the County of Prince Edward at 613.476.2148 ext. 1023, 613.962.9108 ext. 1023, or info@pecounty.on.ca.

Share This:
Share
Tweet
Save

Related News & Notices

Council and Committee of the Whole Highlights – June 9 & 11, 2026

Temporary changes to garbage and recycling collection June 29 – July 1 for Canada Day holiday

Traffic disruptions in Picton for Pride Parade June 20

Agenda now available for June 17 Planning and Development Committee

PECelebrates returns June 14 – July 1

Traffic disruptions on section of County Road 10 (Cherry Valley) June 15