Prince Edward County Municipal Services

Business

Find the info you need on relocating, starting or expanding your business in Prince Edward County.

Visit

Explore what Prince Edward County has to offer for residents and visitors alike.

 

 

County Road 49 rehabilitation report: September 28 – October 2

September 25, 2026

Tomlinson has rubblized and placed gravel on approximately 6.5 km of County Road 49 as of Friday, September 25.

Crews began work at County Road 15 (Northport Road) and have progressed to approximately Lyons Road.

Construction work on County Road 49 is continuing seven days a week from 7 am to 7 pm. The municipality agreed to allow the contractor to work on weekends to make sure the planned road work is completed this year.

Drivers can expect delays of between 5 to 10 minutes. Both lanes of traffic will re-open at the end each construction day. The contractor is applying calcium and water to the gravel sections to suppress the dust.

Rubblization is a road rehabilitation technique that involves breaking the existing concrete road into small pieces and leaving them in place, creating a strong foundation for the new asphalt road. Click here to read more about the process.

The contractor tentatively plans to place new asphalt on the rubblized section of County Road 49 beginning the week of October 5. The municipality will provide further updates closer to the date. Click here to sign up for the email notices.

 Culvert replacement and waterproofing update

Replacement of culverts will be completed by the end of this week.

Waterproofing of existing concrete box culverts will continue to progress towards Picton.

  • During the culvert work, there will be single-lane closures in the vicinity of the work from 7 am – 7 pm. Temporary traffic signals will help maintain the flow of traffic and minimize delays.
  • The municipality reminds drivers that a temporary 60 km/h speed limit is in effect throughout the construction zone. Please follow posted signage and reduce your speed when approaching road cuts.
  • The municipality continues to monitor and maintain areas where the concrete has been cut out and removed for the cross-culvert replacement. “Bump ahead” signs are installed near the road cuts. 

Traffic update

With a 5- to 10-minute wait expected during the major rehabilitation work, using the alternate route instead of staying on County Road 49 may provide little to no advantage for commuters.

However, the municipality recognizes that some drivers may use or continue to use County Roads 5 and 15 as an alternate.

Drivers are reminded to follow all posted speed limits along these roads.

 What residents can expect during construction

Residents and drivers might notice:

  • A machine breaking the existing concrete into rubble.
  • Rollers compacting the roadway.
  • Trucks and paving crews placing new asphalt.
  • Unpleasant odors from the asphalt that could last up to several hours.
  • A smoother road surface once construction is complete.  

Stay up to date

The municipality will provide updates to the public throughout the project. Click here to sign up for the email notices.

Click here to learn more about the project on the County website.

For more information, contact Garrett Osborne, Project Manager, at 613.476.2148 ext. 2002 or gosborne@pecounty.on.ca.

Share This:
Share
Tweet
Save

Related News & Notices

Ministry of Transportation completes study for intersection improvements at Highway 62 and County Road 1

County Road 49 rehabilitation report: September 28 – October 2

Watermain flushing & hydrant maintenance (Picton) September 28 – October 2

County of Prince Edward celebrates outstanding residents with Civic Recognition Awards

REMINDER: 55 King Street parking lot closed beginning September 28

Construction on Ortona Circle (Picton) September 25