Rural road work set to begin in coming weeks

May 20, 2025

 Work on more than 46 km of rural roads will get underway in a few short weeks. County Council approved various tender awards on April 22, as part of the rehabilitation and preventative maintenance program for rural roads across the municipality.

The bulk of this work in 2025 is single surface treatment, also known as tar-and-chip, which is a single layer application. Single surface treatment is a preventative maintenance technique that will extend the life of a surface-treated road surface that is still in good condition.

Twenty-four km of roads will receive a single surface treatment in 2025. Single surface treatment will occur on:

  • County Road 24 (Lighthall Road to Army Reserve Road)
  • Lucks Crossroad (County Road 8 to County Road 17)
  • Massassauga Road (County Road 28 to the end)
  • Sunrise Drive (Massassauga Road to the end)
  • Mitchells Crossroad (County Road 17 to County Road 13)
  • Old Cheese Factory Road (entire length)
  • Quick Short Road (County Road 35 to the end)
  • Walmsley Road (County Road 24 to Bond Road)

Double surface treatment involves rehabilitation of the road surface including pulverizing, base stabilization, and addition of new granular material, followed by a double layer of surface treatment and fog seal. This will occur on:

  • County Road 13 (Civic Address 3641 to Babylon Road at Civic Address 2775 County Road 13)
  • County Road 19 (Civic Address 538 to Cunningham Road at 1101 County Road 19)
  • County Road 35 (County Road 15 to Green Point Lane)

In addition, micro surfacing, another preventative maintenance technique that is used on asphalt road surfaces to restore the road surface and help prevent water from seeping into the road base, which causes deterioration, will be applied on:

  • County Road 12 (Ridge Road to County Road 18)
  • County Road 33 (Henderson Lane to Victoria Road)
  • County Road 4 (Civic Address 1119 to two km north)

All of the work outlined above is scheduled to get underway this spring with expected completion by the end of summer.

In addition to surface treatment and micro surfacing, other contracted maintenance techniques, such as crack sealing and asphalt spot repairs, will also occur this spring and early summer. The Operational Services Department team will also be out this spring with regular maintenance work like street sweeping in settlement areas with curbs and gutters, gravel road resurfacing, and guide rail repairs.

Visit the County website to learn more about road rehabilitation and maintenance. Sign up to receive news and notices including updates on road work. You can also follow the County on Facebook and Twitter for updates.

Share This:
Share
Tweet
Save

Related News & Notices

Are you a youth thinking of running for Council? Free workshop available

Emergency water service repair on Picton Main Street February 11

Several Family Day activities planned for February 16

Council and Committee of the Whole Highlights – January 27 & 29, 2026

Municipal offices closed February 16 for Family Day

Thinking of running for Council? Free workshop available