SP-09-24 (Su)
Request
The County has received an application for Site Plan Control to establish a cannabis production facility at 4309 Highway 62.
Status
Approved
Documents Submitted for Evaluation
Second Submission:
Hydrogeological Study
Environmental Impact Study
Site Plan
Septic Brief
Stormwater Management Brief
Architectural Drawings
Air Treatment Environmental Plan
Traffic Impact Study
First Submission:
Air Treatment Environmental Plan
Septic Brief
Site Plan Drawing Package
Stormwater Management Report
Traffic Impact Study
Hydrogeological Study
Architectural Drawing
Environmental Impact Study
Contact Information
For further information, please contact:
Emily Overholt, Planner
613.476.2148 ext. 2006 | F:613.471.2051
eoverholt@pecounty.on.ca
Mailing address:
332 Picton Main Street
Picton, ON K0K 2T0